|
||||||||||||
Home | History | Photos | Video | Contact us |
||||||||||||
La
This legacy from the second world war is typical of the engineering achievements to be left on British soil by the Germans.
This particular tunnel, designated as a Hohlgang, was conceived and
built to be a fuel store for the eventual re-fueling of U-boats. The
idea of having this fuel‘farm’underground was to
protect it from aerial bombardment as the Germans had experienced some
problems with the RAF bombing fuel tanks adjacent to Castle Cornet. The
U-Boats, were to have been re-fueled in the bay behind the Aquarium
tunnel (which is nearby) and fuel pumped through to the vessels mooring. The
tunnel complex was never completed due to time running out for the
Germans as supplies from
The tunnel bays were designed in such a way that if any of the tanks were ruptured or sprung a leak, the whole of the contents could be contained within the pool beneath each tank or alternatively, the oil would be allowed to drain away through the drains which were installed. Subsequently during the conversion of the tunnel into the museum, the fire .brigade pumped some 1500 gallons of water through one of the drains at full bore, the drain appeared to take it all within its stride and sucked the lot up!
This museum was some two years in the making! After the idea, came the work to transform a dream into a reality. Not an easy thing to do, considering the condition of the tunnel when the feasibility study was undertaken. After this study (when we had satisfied ourselves that it was not only feasible but financially possible), did the real work start with trying to persuade the authorities that it was a good idea. Initially discussions took place with the States of Guernsey Board of Administration during 1986. The response from the Board was favorable. This then enabled us to negotiate with the States Engineers (to ascertain the structural safety of the tunnel), the Island Development Committee, States Building Control and finally back to the Board of Administration. After the above had taken place, some 12 months had passed us by and already the cost of the conversion had risen!
Work
on the conversion started in earnest during December of 1987 on
excavating the tunnel entrances (one to provide a main entrance and the
second to provide an emergency exit).
It had been decided for reasons of safety, to build an extension to the
existing tunnel
lining to afford protection in case of falling debris from the cliff
face. In addition, steps and vehicle ramps were incorporated into the
design and built. The back connecting tunnel between the fuel tank bays
had to be completed. This was to enable our prospective visitors to
view the unfinished tunnel in safety. While all of this was 'going on',
sub contractors were being organized to; completely re-wire the
complex, install air conditioning, fit smoke detectors, fit emergency
lights, fit the alarm system, fit fire alarms, spray paint the whole
interior and of course the one remaining fuel tank had to be 'sorted
out'! In order to make the fuel tank safe, it was necessary to pump the
remaining 500 gallons of fuel out and fill it with water (to prevent
explosive gases from 'lingering). However, the supports underneath the
tank were then deemed to be unsafe and so new block support walls had
to be built. In order to prevent further rusting of this monumental
edifice, it had to be descaled and sprayed with a rust preventative
priming paint to arrest the decaying process. After all this of course,
the cabinets had to be made and lined, wired up and glazed. Following
which dummies had to be dressed, Exposed tunnel
lining
description cards had to be organized, pieces for uniforms had to be
found to complete those that were lacking of something or other and of
course the restoration of many of the exhibits which are on display was
being undertaken. The original date for opening was to have been during
April 1988. However, after some delay the
museum finally opened its doors during the last days of August 1988.
|
||||||||||||